CROSSWORD 10  

PMP, สอบ PMP, knowledger, knowledgertraining

Across

1.       A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

2.       One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.

3.       A temporary endeavor undertaken to create a unique product, service, or result.

4.       A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

Down

1.       A statistical method for identifying which factors may influence specific variables of a product or process under development or in production.

2.       Techniques used to shorten the schedule duration without reducing the project scope.

3.       The stakeholder management plan is a subsidiary plan of the project management plan that defines the processes, procedures, tools, and techniques to effectively engage stakeholders in project decisions and execution based on the analysis of their needs, interests, and potential impact.

4.       A systematic procedure, technique, or process used to transfer information among project stakeholders.


 KEY

Project Management Training, Knowledger Training, Knowledger, PMP

 Across

1.                   Decision Tree Analysis

2.                   Activity Code

3.                   Project

4.                   Change Control Board

Down

1.                   Design of Experiments

2.                   Schedule Compression

3.                   Staffing Management Plan

4.                   Communication Methods